Lakeview Avenue Grade Separation
This project constructed the grade separation of Lakeview Avenue over Orangethorpe Avenue and the Burlington Northern Santa Fe Railway tracks by constructing a 4-lane overcrossing bridge. The project also included the construction of a 4-lane bridge over Atwood Channel.
The project included:
Approximately 45,000 square feet of Mechanically Stabilized Earth (MSE) Walls.
Two bridges, one consisting of Cast-In-Place (CIP) Bulb Tee Girders and the other consisting of precast concrete girders.
Jack/bore operations underneath the BNSF railroad and the Atwood channel.
Construction of a precast underground retention basin