Lakeview Avenue Grade Separation 

This project constructed the grade separation of Lakeview Avenue over Orangethorpe Avenue and the Burlington Northern Santa Fe Railway tracks by constructing a 4-lane overcrossing bridge. The project also included the construction of a 4-lane bridge over Atwood Channel.


The project included:


  • Approximately 45,000 square feet of Mechanically Stabilized Earth (MSE) Walls.

  • Two bridges, one consisting of Cast-In-Place (CIP) Bulb Tee Girders and the other consisting of precast concrete girders.

  • Jack/bore operations underneath the BNSF railroad and the Atwood channel.

  • Construction of a precast underground retention basin